Grand Parkway stretch in W. Harris Co. not so shovel-ready after all
Created on 10/12/09Harris County officials will ask the state to shift $181 million in federal stimulus funding from a controversial toll road portion of the Grand Parkway to other local projects, citing delays obtaining federal permits that might never be issued.
This summer,
The proposed re-allocation was hailed by transportation activists and environmentalists, including some who believe difficulty obtaining a wetlands permit could halt, not only the 15 mile segment E, but scuttle the rest of the proposed 180 mile loop through seven counties.
County Judge Ed Emmett, who as a state legislator in the mid 1980s sponsored legislation creating the Grand Parkway, said the smaller toll road project is vital to county transportation needs and he was confident it will be built.
"It's still going to happen," Emmett said. "This is in no way a crippling blow to segment E. It's not even a damaging blow. We thought we were going to have some stimulus money, and now we won't have that."
The stimulus funds are supposed to be used for shovel-ready projects, those that are closest to actual construction, but awaiting funding to begin. Last March, the county let about $10 million in engineering projects to get segment E shovel-ready.
Delay in permit
The recommendation that the county withdraw the project from the Texas Department of Transportation's list of stimulus projects was made by Art Storey, who heads the county's Public Infrastructure Department.
"Staff and consultants have worked diligently and successfully to be on schedule to meet the deadlines to enable Segment E construction to qualify for and receive the stimulus funding, but the federal permit from the U.S. Army Corps of Engineers cannot be completely processed by the required mid-February date," Storey said in a letter to the court this week. "In fact, because of conflicts over environmental impacts and mitigation, that permit might never be issued."
TxDOT spokesman Chris Lippincott said the department would wait for a vote of
"We work with the
Commissioner Steve Radack, whose Precinct 3 contains the proposed segment E, described the loss of stimulus funds as a "huge" development in the decades-long saga of the
"When it comes to expecting
The U.S. Fish and Wildlife Service and the
"We are encouraged that Judge Emmett and the Harris County commissioners now recognize they need to take the time necessary to ensure that irreparable damage not be done to this great regional ecological resource, the Katy prairie, by the development of Segment E of the Grand Parkway," said Mary Anne Piacentini, executive director of the Katy Prairie Conservancy.
'Welcome news'
"This is stupendous news" said David Crossley, president of the non-profit Houston Tomorrow. "The
Robin Holzer, chair of the Citizens Transportation Coalition, an advocacy group that opposes the
"We knew last March that Segment E wasn't shovel-ready, so it's good that everyone else has figured that out," she said.
Chronicle reporter Mike Snyder contributed to this story.